Project

General

Profile

Activity

From 06 Mar 2017 to 04 Apr 2017

04 Apr 2017

04:58 PM 7.00 hours (Project: Miscellaneous Activities)
Configureing and Installing of the required setup for the System with help taken from Rama Krishnam Raju

03 Apr 2017

06:40 PM 1.00 hour (Project: Miscellaneous Activities)
Helped to team members for dongle update. Snehal Patil
04:59 PM 4.00 hours (Task #1445 (Closed): Testing question & answers)
Testing interview question paper Avinash Pandey

31 Mar 2017

06:12 PM 1.00 hour (Task #1319 (Closed): Start Analyze recording using Mediaooks sdk (Mainly Hardware based))
Parag Gandhi
06:00 PM 2.50 hours (Task #1399 (Closed): Preparation of KRA, Reporting format, workflow and summery of al...
Parag Gandhi
05:01 PM 0.50 hour (Project: Miscellaneous Activities)
Attended the Demo of the AmazeMe related to common input renderer. Krishnam Raju
04:54 PM 1.50 hour (Project: Miscellaneous Activities)
Annual Review meeting with ParagSir, RohitSir, PandeySir. Abhijit Pawar
04:53 PM 6.50 hours (Task #1018 (Closed): Training of wxWidgets)
Training of wxWidgets Abhijit Pawar
04:16 PM 4.00 hours (Task #1395 (Closed): Creating report of all the team member for the financial year 20...
Prepared KRA, Wrokflow of team, Team Structure and created report of all the team members related to their tasks and ... Debashis Bhandari
04:12 PM 2.00 hours (Task #1365 (Closed): Review of Candidates who has not yet completed the one year in t...
Taken review of Prashant Nikam along with Rohit, Amit. Taken review of Rahul Ranjan along with Rohit and Avinash. Debashis Bhandari
03:45 PM 4.00 hours (Task #1397 (Closed): Review)
Review Avinash Pandey
02:38 PM 3.00 hours (Task #1421 (Closed): Review of developers who completed one year in the organization.)
Parag Gandhi

30 Mar 2017

06:05 PM 3.00 hours (Task #1319 (Closed): Start Analyze recording using Mediaooks sdk (Mainly Hardware bas...
Parag Gandhi
05:56 PM 2.00 hours (Task #1397 (Closed): Review)
Technical & Non technical requirements for NLE Avinash Pandey
05:51 PM 1.50 hour (Task #1397 (Closed): Review)
Review of Amrendra Kumar Avinash Pandey
05:51 PM 8.00 hours (Project: Miscellaneous Activities)
learning and reading audio concepts. Debugging in NLE solution Snehal Patil
05:48 PM 2.00 hours (Task #1399 (Closed): Preparation of KRA, Reporting format, workflow and summery of al...
Parag Gandhi
04:43 PM 8.00 hours (Project: Miscellaneous Activities)
wxWidgets Sample Application studying for Editor Product Preparation Reading some CPP concepts and cleared doubts in ... Abhijit Pawar
04:29 PM 1.50 hour (Project: Miscellaneous Activities)
Review Bhagyashree Raut
04:28 PM 1.00 hour (Task #1421 (Closed): Review of developers who completed one year in the organization.)
Parag Gandhi

29 Mar 2017

06:08 PM 1.50 hour (Task #1421 (Closed): Review of developers who completed one year in the organization.)
Parag Gandhi
06:07 PM 6.00 hours (Task #1319 (Closed): Start Analyze recording using Mediaooks sdk (Mainly Hardware bas...
Parag Gandhi
05:32 PM 3.50 hours (Task #1397 (Closed): Review)
Listing of development Avinash Pandey
05:25 PM 8.00 hours (Project: Miscellaneous Activities)
Discussion with team member about audio concepts and learning and reading mono, stero audio concepts. Snehal Patil
05:00 PM 4.00 hours (Project: Miscellaneous Activities)
wxWidgets Sample Application studying for Editor Product Preparation. Abhijit Pawar
04:51 PM 1.00 hour (Task #1365 (Closed): Review of Candidates who has not yet completed the one year in th...
Did performance review of Bhagyashree Raut along with Parag and Amit. Debashis Bhandari
02:22 PM 1.00 hour (Support #1434 (Closed): Support given to Egypt dealer to change 0117 dongle and board ...
1.Given support to Egypt dealer to change Leo HD 0117 dongle and board to 0284. Taken machine online in teamviewer. Debashis Bhandari

27 Mar 2017

06:04 PM 5.00 hours (Task #1319 (Closed): Start Analyze recording using Mediaooks sdk (Mainly Hardware bas...
Parag Gandhi
05:58 PM 3.00 hours (Task #1399 (Closed): Preparation of KRA, Reporting format, workflow and summery of al...
Parag Gandhi
05:24 PM 8.00 hours (Project: Miscellaneous Activities)
Disscussed with tester about 8.0 requirements. Done testing of av track functionality. Snehal Patil
08:20 AM 12.00 hours (Task #905 (In Progress): Activities for Uttam Kamkar)
3rd day of Cabsat exhibiton Uttam Kamkar
08:19 AM 11.00 hours (Task #905 (In Progress): Activities for Uttam Kamkar)
2nd day of Cabsat exhibiton Uttam Kamkar
08:17 AM 11.00 hours (Task #905 (In Progress): Activities for Uttam Kamkar)
1st day if Cabsat exhibito Uttam Kamkar
08:07 AM 12.00 hours (Task #905 (In Progress): Activities for Uttam Kamkar)
Setup stall at Cabsat Uttam Kamkar
08:05 AM 16.00 hours (Task #905 (In Progress): Activities for Uttam Kamkar)
Travel to Dubai for Cabsat 2017 Uttam Kamkar

24 Mar 2017

04:51 PM 7.00 hours (Project: Miscellaneous Activities)
wxWidgets Sample Application studying for Editor Product Preparation. Abhijit Pawar
03:59 PM 3.00 hours (Task #1421 (Closed): Review of developers who completed one year in the organization.)
Parag Gandhi
03:38 PM 6.00 hours (Task #1397 (Closed): Review)
Review Avinash Pandey

23 Mar 2017

05:49 PM 1.00 hour (Task #1399 (Closed): Preparation of KRA, Reporting format, workflow and summery of all...
Parag Gandhi
05:44 PM 0.00 hour (Support #1402 (Closed): Visit to Mumbai Photographer Exhibition at NSE ground)
we visited Exhibiton yesterday 22/03/2017 Parag Gandhi
05:08 PM 5.00 hours (Task #1397 (Closed): Review)
Review Avinash Pandey
08:23 AM 4.00 hours (Task #1397 (Closed): Review)
Attended NVFF (Exhibition) Avinash Pandey
08:19 AM 2.00 hours (Task #1397 (Closed): Review)
Reviewe for Krishnam Raju Avinash Pandey
04:54 PM 8.00 hours (Project: Miscellaneous Activities)
Input matrix switcher dialog input row and column lock / unlock button code change for optimize it. Abhijit Pawar
04:53 PM 3.50 hours (Task #1395 (Closed): Creating report of all the team member for the financial year 20...
Creating report of self and peers related to features worked on, bugs solved in various projects. Prepared KRA for th... Debashis Bhandari
04:40 PM 4.50 hours (Task #1365 (Closed): Review of Candidates who has not yet completed the one year in t...
Participated in review of Nilesh sinkar, Ankush Wadke, and Punit Shah. Debashis Bhandari
03:53 PM 1.00 hour (Task #1412 (New): Review Of Peers)
Review : Sharan Varghese Rohit Gonsalves
03:53 PM 1.00 hour (Task #1412 (New): Review Of Peers)
Review : Shrikant Savaji Rohit Gonsalves
03:51 PM 1.00 hour (Task #1412 (New): Review Of Peers)
Review : Bhagyashree Jagtap Rohit Gonsalves
03:51 PM 1.00 hour (Task #1412 (New): Review Of Peers)
Review : Ankush Wadke Rohit Gonsalves
03:51 PM 1.00 hour (Task #1412 (New): Review Of Peers)
Review : Nilesh Shinkar Rohit Gonsalves

22 Mar 2017

04:47 PM 8.00 hours (Project: Miscellaneous Activities)
Reading WxWidgets documents related to work . Abhijit Pawar
04:47 PM 8.00 hours (Task #1395 (Closed): Creating report of all the team member for the financial year 20...
Creating report of my team members for the financial year 2016-2017. Debashis Bhandari
04:43 PM 1.00 hour (Project: Miscellaneous Activities)
Attended Review Meeting. Krishnam Raju
01:11 PM 4.00 hours (Support #1402 (Closed): Visit to Mumbai Photographer Exhibition at NSE ground)
Parag Gandhi
01:08 PM 0.50 hour (Task #1399 (Closed): Preparation of KRA, Reporting format, workflow and summery of all...
Parag Gandhi
01:05 PM 1.50 hour (Task #1370 (Closed): Review of developers who has not yet completed the one year in th...
Parag Gandhi

21 Mar 2017

07:21 PM 4.00 hours (Project: Miscellaneous Activities)
Preparing report of work done for the financial year 2016 -2017 Prashant Nikam
05:25 PM 1.00 hour (Task #1399 (Closed): Preparation of KRA, Reporting format, workflow and summery of all...
Parag Gandhi
05:12 PM 7.50 hours (Task #1397 (Closed): Review)
Worked on the task Avinash Pandey
05:11 PM 0.50 hour (Task #1370 (Closed): Review of developers who has not yet completed the one year in th...
Parag Gandhi
04:43 PM 1.50 hour (Task #1370 (Closed): Review of developers who has not yet completed the one year in th...
Parag Gandhi
01:28 PM 1.50 hour (Task #1370 (Closed): Review of developers who has not yet completed the one year in th...
Parag Gandhi
04:56 PM 3.00 hours (Task #1395 (Closed): Creating report of all the team member for the financial year 20...
1.Defined KRA of my Team. Created Team Structure and Creating report of features and bugs worked on by team for the f... Debashis Bhandari
04:38 PM 3.00 hours (Task #1394 (Closed): Interview for Software Testing Engineer.)
Interview conducted for Prachi, Divya, Sashank along with Avinash and Pratibha. Debashis Bhandari
04:31 PM 2.00 hours (Task #1365 (Closed): Review of Candidates who has not yet completed the one year in t...
Review Gourisankar Samal along with Parag and Avinash. Debashis Bhandari

20 Mar 2017

05:43 PM 2.50 hours (Task #1391 (In Progress): Meeting with Mr. Rahul Deshmukh)
Discuss next financial year project-task, resource allocation, testing team management with Mr. Rahul Deshmukh and ot... Debashis Bhandari
05:41 PM 2.00 hours (Task #1388 (Closed): Review for Shrikant savaji)
Review meeting for Shrikant Savaji Avinash Pandey
05:40 PM 2.50 hours (Task #1390 (Closed): Meeting with Mr. Rahul Deshmukh)
Meeting with Rahul Deshmukh Avinash Pandey
04:58 PM 2.50 hours (Administration #1387 (Closed): Meeting with Mr. Rahul Deshmukh and Viren Sir)
Parag Gandhi
04:52 PM 2.50 hours (Task #1370 (Closed): Review of developers who has not yet completed the one year in t...
Parag Gandhi
04:51 PM 8.00 hours (Project: Miscellaneous Activities)
AmezeMe Input Matrix Dialog is completed with all given requirement from PandeySir and PunitSir. Abhijit Pawar

18 Mar 2017

09:40 AM 1.00 hour (Administration #1383 (Closed): Communication with krishna and Prashant related to bitm...
Communicating with Krishna waring regarding the bitmaps required, suggested corrections in the bitmaps and layout for... Debashis Bhandari

16 Mar 2017

05:58 PM 1.00 hour (Task #1300 (Closed): Discuss Split File- Lipsync issue in LeoHD-Egypt.)
Parag Gandhi
05:00 PM 8.00 hours (Project: Miscellaneous Activities)
Input Matrix switcher Optimize the code of Switching streams and bus with PunitSir Abhijit Pawar

15 Mar 2017

07:52 PM 2.00 hours (Task #1367 (Closed): Security implementation in Verticast Reallia.)
1.Compiled security lib in 2015. 2.Added security source code in SVN. 3.Implemented code to run Virticast Realliz app... Debashis Bhandari
07:44 PM 2.00 hours (Task #1372 (Closed): Training to program or initialize Twister HD and Leo HD BOB and ...
1.Created new master dongle for Deepak to Programme THD BOB + Dongle and Leo HD Board + dongle. 2.Created document, h... Debashis Bhandari
07:34 PM 3.50 hours (Task #1365 (Closed): Review of Candidates who has not yet completed the one year in t...
Taken review of Swapnil and Kuldip. Debashis Bhandari
05:36 PM 0.50 hour (Task #1300 (Closed): Discuss Split File- Lipsync issue in LeoHD-Egypt.)
Parag Gandhi
05:26 PM 3.50 hours (Task #1370 (Closed): Review of developers who has not yet completed the one year in t...
Parag Gandhi
05:04 PM 2.00 hours (Task #1369 (Closed): Review for Swapnil S Kulkarni)
Participated in review of Swapnil S Kulkarni with Debashis & Parag Avinash Pandey
05:00 PM 8.00 hours (Project: Miscellaneous Activities)
Input Matrix switcher dialog input row and column enable and disable for single row and column extend some task in it... Abhijit Pawar

14 Mar 2017

05:04 PM 2.00 hours (Task #1300 (Closed): Discuss Split File- Lipsync issue in LeoHD-Egypt.)
Parag Gandhi
05:02 PM 2.50 hours (Task #1367 (Closed): Security implementation in Verticast Reallia.)
Made changes in source code to compile THDSecureLib project in 2015. Debashis Bhandari
05:00 PM 8.00 hours (Project: Miscellaneous Activities)
Input Matrix switcher dialog input row and column enable and disable for single row and column extend some task in it... Abhijit Pawar
04:56 PM 1.00 hour (Task #1365 (Closed): Review of Candidates who has not yet completed the one year in th...
Taken Review of Varra Srinivas Reddy along with AK and TC. Debashis Bhandari

11 Mar 2017

04:52 PM 4.00 hours (Task #1358 (Closed): Meeting with Hebiz, CMD, Uttam, Rahul Deshmukh, and other Projec...
Attended meeting. Debashis Bhandari
04:35 PM 4.00 hours (Task #1357 (Closed): Meeting With Mr. Hebiz regarding Octa4K development status and N...
Parag Gandhi
04:32 PM 0.50 hour (Task #1300 (Closed): Discuss Split File- Lipsync issue in LeoHD-Egypt.)
Parag Gandhi

10 Mar 2017

04:53 PM 5.00 hours (Project: Miscellaneous Activities)
Input Matrix switcher dialog input row and column enable and disable for single row and column extend some task in it... Abhijit Pawar
01:42 PM 1.00 hour (Task #1300 (Closed): Discuss Split File- Lipsync issue in LeoHD-Egypt.)
Parag Gandhi

09 Mar 2017

05:55 PM 1.50 hour (Task #1300 (Closed): Discuss Split File- Lipsync issue in LeoHD-Egypt.)
Parag Gandhi
05:07 PM 4.00 hours (Project: Miscellaneous Activities)
Checked the InputMatrix Code with Abhijith and Intigrated the same in to mine. Discused about the more functionalitys. Krishnam Raju
04:49 PM 8.00 hours (Project: Miscellaneous Activities)
Input Matrix switcher dialog input row and column enable and disable for single row and column extend some task in it... Abhijit Pawar

08 Mar 2017

05:41 PM 0.50 hour (Task #1300 (Closed): Discuss Split File- Lipsync issue in LeoHD-Egypt.)
Parag Gandhi
04:47 PM 8.00 hours (Project: Miscellaneous Activities)
Input Matrix switcher dialog input row and column enable and disable for single row and column extend some task in it... Abhijit Pawar

07 Mar 2017

05:23 PM 1.00 hour (Task #1300 (Closed): Discuss Split File- Lipsync issue in LeoHD-Egypt.)
Parag Gandhi
04:52 PM 8.00 hours (Project: Miscellaneous Activities)
Input Matrix switcher dialog input row and column enable and disable for single row and column extend some task in it... Abhijit Pawar

06 Mar 2017

05:47 PM 2.00 hours (Task #1319 (Closed): Start Analyze recording using Mediaooks sdk (Mainly Hardware bas...
Parag Gandhi
04:53 PM 8.00 hours (Project: Miscellaneous Activities)
Input Matrix switcher dialog input row and column enable and disable for single row and column extend some task in it... Abhijit Pawar
 