Project

General

Profile

Activity

From 18 Aug 2016 to 16 Sep 2016

16 Sep 2016

06:14 PM 0.50 hour (Project: Miscellaneous Activities)
Discuss new freshers induction program with Chelna, Rohit, Avinash adn Debashish Parag Gandhi
05:20 PM 0.50 hour (Project: Miscellaneous Activities)
Attended meeting called by HR Avinash Pandey
04:50 PM 0.50 hour (Project: Miscellaneous Activities)
Meeting with Chelna, AP, RG and PG related new joinees from C-DAC for product training and introduction. Debashis Bhandari
04:48 PM 1.00 hour (Project: Miscellaneous Activities)
Reading Twister Octa 4K Specification Document. Debashis Bhandari
04:45 PM 4.00 hours (Project: Miscellaneous Activities)
Meeting with PowerCreator education solution from China Uttam Kamkar
02:14 PM 4.00 hours (Project: Miscellaneous Activities)
Visited info Comm exhibition (Meeting with Mr. Devin of Power Creator) Avinash Pandey

14 Sep 2016

05:00 PM 1.50 hour (Project: Miscellaneous Activities)
Solved problem of application start on Praneeths system. Bhagyashree Raut
04:50 PM 4.00 hours (Project: Miscellaneous Activities)
Analysed Panther application. Checked Recording, Input Output delay, Effect loading, Fx Sequencer, MS, Logo, Scroll T... Debashis Bhandari
01:48 PM 4.00 hours (Project: Miscellaneous Activities)
Analysing Panther HD Product of Rukuss solution along with UK, RG and PG. Debashis Bhandari
12:47 PM 1.50 hour (Project: Miscellaneous Activities)
Discussion regarding agreement and VPANG. Rohit Gonsalves
07:58 AM 1.50 hour (Project: Miscellaneous Activities)
VPang: DIscussed with team bugs list given by Kim Uttam Kamkar

13 Sep 2016

05:29 PM 1.00 hour (Project: Miscellaneous Activities)
Analyzing competitors product and its features Parag Gandhi
04:45 PM 2.00 hours (Project: Miscellaneous Activities)
Meeting for Vpang with UK, RG, DB, PS, CB. Bhagyashree Raut
04:41 PM 2.00 hours (Project: Miscellaneous Activities)
Meeting with UK, RG, BR, CB, PS related to VPang product development and bug solving. Debashis Bhandari

12 Sep 2016

04:54 PM 2.50 hours (Project: Miscellaneous Activities)
Analyzing problem of compositionconvertor.exe (Utility to encrypt TwisterPro effects with pack codes )not working in ... Debashis Bhandari
04:53 PM 1.00 hour (Project: Miscellaneous Activities)
Meeting with CMD to update on all products Uttam Kamkar

09 Sep 2016

04:30 PM 6.50 hours (Task #451 (Closed): To prepare new utility for encryption of Twister Pro effects with...
Created new utility to encrypt Twister Pro effects with pack codes. Debashis Bhandari

08 Sep 2016

04:53 PM 3.50 hours (Task #451 (Closed): To prepare new utility for encryption of Twister Pro effects with...
Implemented code to encrypt Twister Pro Effects. Debashis Bhandari

07 Sep 2016

04:51 PM 5.00 hours (Task #451 (Closed): To prepare new utility for encryption of Twister Pro effects with...
Setting up machine and configuration. Debashis Bhandari
11:11 AM 2.00 hours (Project: Miscellaneous Activities)
Helping Jignesh to prepare Twister HD 5.4 setup. Implementing code for proper checking of versions during installation. Debashis Bhandari

05 Sep 2016

12:41 PM 1.00 hour (Project: Miscellaneous Activities)
Interview of Gauri Shankar Avinash Pandey
11:46 AM 1.00 hour (Project: Miscellaneous Activities)
Conducting F-2-F Interview round for GouriShankar., along with Avinash Pandey. Amit Khobragade

01 Sep 2016

04:08 PM 2.00 hours (Project: Miscellaneous Activities)
Attended meeting with Viren sir, Ajit Bhai, Deepak, Parag and Jignesh related to Egypt's issue. Debashis Bhandari
04:07 PM 5.00 hours (Project: Miscellaneous Activities)
Analyzing problem of input getting stuck in Egypt's customer machine. Setting the same environment at our side to re-... Debashis Bhandari

31 Aug 2016

09:26 PM 8.00 hours (Project: Miscellaneous Activities)
Attending Mass Recruitment Drive by Company at CDAC, Juhu. Amit Khobragade
05:04 PM 10.00 hours (Project: Miscellaneous Activities)
Visit CDAC Mumbai center for Recruitment of freshers. Taken six 2nd round of interviews with Amit. Parag Gandhi
04:49 PM 8.00 hours (Project: Miscellaneous Activities)
Taken machine of Mr. Ahmed Barkar(Egypt customer) online to analyse Strobic problem of input 3 and 4. Debashis Bhandari
04:47 PM 9.00 hours (Project: Miscellaneous Activities)
Campus interview selection at C-DAC Juhu. Was there for conducting examination and then to paper checking, 1st and 2n... Rohit Gonsalves
04:20 PM 11.00 hours (Project: Miscellaneous Activities)
Campus recruitment C-DAC Juhu Avinash Pandey
09:23 AM 9.00 hours (Project: Miscellaneous Activities)
Been to CDAC VITA Juhu for conducting interviews. Ankush Wadke
09:13 AM 8.00 hours (Project: Miscellaneous Activities)
Taken interviews of freshers at C-DAC (Juhu) Punit Shah
08:56 AM 9.00 hours (Project: Miscellaneous Activities)
Attended the recruitment drive for freshers from C-DAC Juhu. Debashis Bhandari

29 Aug 2016

05:50 PM 4.00 hours (Project: Miscellaneous Activities)
Preparing for change in Test question paper sets, and also finalizing the same. Amit Khobragade
05:49 PM 1.00 hour (Project: Miscellaneous Activities)
Attend Meeting called by Avinash for Interview drive at CDAC,Juhu. Amit Khobragade
05:11 PM 2.00 hours (Project: Miscellaneous Activities)
Discuss tomorrow Mumbai CDAC recuritment process Parag Gandhi
05:07 PM 1.00 hour (Project: Miscellaneous Activities)
In necessary planning and coordination for recruitment drive Avinash Pandey
05:05 PM 2.00 hours (Project: Miscellaneous Activities)
Meeting to discuss schedule the recruitment drive of C-DAC Bandra/Juhu Avinash Pandey
05:01 PM 2.00 hours (Project: Miscellaneous Activities)
Meeting for Interview schedule planning. Ankush Wadke
04:59 PM 1.00 hour (Project: Miscellaneous Activities)
Correcting Twister HD and Leo HD brochure content Debashis Bhandari
04:49 PM 2.00 hours (Project: Miscellaneous Activities)
Meeting for recruitment drive at CDAC Rohit Gonsalves
04:49 PM 1.00 hour (Project: Miscellaneous Activities)
Attended meeting for the recruitment drive for freshers from C-DAC Bandra/Juhu. Debashis Bhandari
04:48 PM 1.00 hour (Project: Miscellaneous Activities)
Taken interview of Jothi. Debashis Bhandari
11:41 AM 1.00 hour (Project: Miscellaneous Activities)
Attended meeting for the recruitment drive for freshers from C-DAC Bandra/Juhu. Debashis Bhandari

26 Aug 2016

03:53 PM 1.50 hour (Project: Miscellaneous Activities)
Setting up Bhagyashree's machine for development of Hex HD. Debashis Bhandari
03:30 PM 2.00 hours (Project: Miscellaneous Activities)
Reading new broucher created by Laxman, suggested to add new features in it and maid new correction. Debashis Bhandari

25 Aug 2016

05:08 PM 1.00 hour (Project: Miscellaneous Activities)
Meeting with Rahul Deshmukh on future strategies for development Avinash Pandey

24 Aug 2016

04:35 PM 0.50 hour (Project: Miscellaneous Activities)
Discussion with Chelna regarding new joinee KrishnaMRaju. Discussion with Rashesh regarding setting up of two new mac... Debashis Bhandari

23 Aug 2016

04:43 PM 1.00 hour (Project: Miscellaneous Activities)
Conducting Skype Interview round for Krishnaraja., along with Debashish Bhandari. Amit Khobragade
04:37 PM 1.00 hour (Project: Miscellaneous Activities)
Taken Skype technical interview of Krishna M Raju. Debashis Bhandari

22 Aug 2016

02:25 PM 1.00 hour (Task #475 (Closed): Telephonic interview of Satish Sampath kumar.)
Taken Interview of Satish. Debashis Bhandari
02:24 PM 1.00 hour (Administration #476 (Closed): Interview )
Telephonic interview of Satish Sampath kumar Avinash Pandey

19 Aug 2016

05:21 PM 1.00 hour (Project: Miscellaneous Activities)
Help to Mehul Nandu, for Restoring SVN backup for TwisterPro project. Amit Khobragade
04:53 PM 1.00 hour (Project: Miscellaneous Activities)
Leo HD Egypt related issues discussed with team and conclusion is done for the dev travel to Egypt to know and unders... Rohit Gonsalves
04:44 PM 1.00 hour (Project: Miscellaneous Activities)
Discuss Egypt LeoHD problems with Uttam, Jignesh, Debashish, Ajitbhai and Rohit Parag Gandhi
04:29 PM 0.50 hour (Project: Miscellaneous Activities)
Discussion related to Twister Pro Source code in SVN along with Mehul Nandu and Amit Khobragade. Debashis Bhandari
02:46 PM 1.00 hour (Task #469 (Closed): To take interview of Krishnamraju.)
Taken interview of Krishnamraju. Debashis Bhandari
02:15 PM 0.00 hour (Task #451 (Closed): To prepare new utility for encryption of Twister Pro effects with ...
This task may be delayed as Twister Pro machine motherboard is not working. Sent for repair. Debashis Bhandari
 

Also available in: Atom