10 Aug 2016

08:58 AM Miscellaneous Activities 0.00 hour (Task #287 (Closed): Handover machine and setup of Leo HD and Twister HD machine in pune.)
Machines installed at pune. Debashis Bhandari

09 Aug 2016

02:20 PM Miscellaneous Activities 2.00 hours (Administration #353 (Closed): Technical interviews )
Candidate Selected. Amit Khobragade
02:12 PM Miscellaneous Activities 2.00 hours (Administration #386 (Closed): Technical interviews )
Conducted technical interview with Amit Avinash Pandey

08 Aug 2016

09:13 PM Miscellaneous Activities 1.00 hour (Administration #387 (Closed): Attend Meeting for Rohit's Team.)
Attend Meeting, and Review Redmine usage activities. Amit Khobragade
05:11 PM Redmine Support 1.00 hour (Support #178 (Closed): Miscellaneous Support)
Misc. Support. Amit Khobragade
04:59 PM Miscellaneous Activities 8.00 hours (Project: Miscellaneous Activities)
Combination of different work like reading, discussion,meeting. Rahul Ranjan
04:59 PM Miscellaneous Activities 2.00 hours (Support #382 (Closed): Meeting related to Leo HD Jerk while loading effect at 90% of ...
Debashis Bhandari
04:56 PM Redmine Support 2.00 hours (Support #383 (Closed): Meeting with RD.)
Redmine Implementations Status Discussions. Amit Khobragade
04:52 PM Miscellaneous Activities 5.00 hours (Project: Miscellaneous Activities)
Meeting with management to discuss: Media looks problems and ways to solve it. A dedicated team is assigned on this t... Uttam Kamkar
02:15 PM Miscellaneous Activities 2.00 hours (Task #378 (Closed): Technical interviews )
Skype Round for Pavan Kumar Amit Khobragade
11:45 AM Miscellaneous Activities 2.00 hours (Task #378 (Closed): Technical interviews )
Conducted technical interview with Amit Avinash Pandey

05 Aug 2016

04:55 PM Miscellaneous Activities 8.00 hours (Project: Miscellaneous Activities)
Rahul Ranjan

04 Aug 2016

05:18 PM Redmine Support 3.50 hours (Support #178 (Closed): Miscellaneous Support)
Optimizing Redmine. Amit Khobragade

03 Aug 2016

05:31 PM Miscellaneous Activities 2.00 hours (Task #352 (Closed): Technical interviews )
Technical Interview Avinash Pandey
04:48 PM Miscellaneous Activities 1.00 hour (Project: Miscellaneous Activities)
Discussion with Gygabyte Representative for our product testing against their motherboards.They will also supply us n... Rohit Gonsalves

02 Aug 2016

02:32 PM Redmine Support 1.00 hour (Support #303 (Closed): For Pune Development Team)
1) Discussion w/Raju Warik, for Karizma StudioERP for Product Manager Role. 2) Creating pending users for the same. 3... Amit Khobragade
01:54 PM Miscellaneous Activities 0.00 hour (Task #264 (Closed): Technical interviews )
Resolved. Vinod Bholla

01 Aug 2016

04:44 PM Miscellaneous Activities 2.00 hours (Project: Miscellaneous Activities)
Started Learning DirectX 12. Read the MSDN regarding how to use new DirectX 12. Difference between DX11 and DX12. Rohit Gonsalves
01:25 PM Redmine Support 4.00 hours (Support #303 (Closed): For Pune Development Team)
Workflow check and Design for Pune Team. Amit Khobragade

29 Jul 2016

03:28 PM Miscellaneous Activities 1.00 hour (Project: Miscellaneous Activities)
THD support and bug solving requirements are discussed with Mr. Hebisz. Rohit Gonsalves

28 Jul 2016

06:15 PM Miscellaneous Activities 2.00 hours (Task #264 (Closed): Technical interviews )
Taken Interview for two candidates. Vinod Bholla
04:30 PM Miscellaneous Activities 1.00 hour (Task #290 (Closed): Decrypt 5 Twister HD effect files for Ajit Bhai.)
Task completed files de crypted and given to Ajit Bhai Debashis Bhandari
04:22 PM Miscellaneous Activities 2.00 hours (Task #266 (Closed): To take telephonic Interview.)
Taken interview of Venkatareddy and Krishna. Debashis Bhandari
03:09 PM Miscellaneous Activities 0.00 hour (Task #287 (Closed): Handover machine and setup of Leo HD and Twister HD machine in pune.)
Complete. Prashant Nikam
03:06 PM Miscellaneous Activities 2.00 hours (Task #287 (Closed): Handover machine and setup of Leo HD and Twister HD machine in pu...
1. Set Up machine to new place in pune office. 2, Introduction with pune staff & co-ordination to set up the stuff. Prashant Nikam
03:02 PM Miscellaneous Activities 2.00 hours (Task #287 (Closed): Handover machine and setup of Leo HD and Twister HD machine in pu...
Dismental my both machines and handed over to Logistic team for shifting to pune office. Prashant Nikam
12:08 PM Miscellaneous Activities 2.00 hours (Task #286 (Closed): Interveiw)
Conducted technical interview with Amit Avinash Pandey
11:24 AM Miscellaneous Activities 2.00 hours (Task #286 (Closed): Interveiw)
Conducting Skype Interviews - 2nd round. Amit Khobragade

27 Jul 2016

04:34 PM Miscellaneous Activities 3.00 hours (Task #264 (Closed): Technical interviews )
Taken Interview for three candidates Manoj, Venkata and Joythi. Vinod Bholla
04:15 PM Miscellaneous Activities 3.00 hours (Task #266 (Closed): To take telephonic Interview.)
Taken Interview of Manoj, Venkata and Joythi. Debashis Bhandari

26 Jul 2016

04:40 PM Miscellaneous Activities 1.00 hour (Task #264 (Closed): Technical interviews )
Interviewed for one candidate. Vinod Bholla
04:40 PM Miscellaneous Activities 4.00 hours (Project: Miscellaneous Activities)
Review of the Bug report for MEdia looks implementation by testers. We assumed two important bugs pending. DDR Loop i... Rohit Gonsalves
04:21 PM Miscellaneous Activities 1.00 hour (Task #266 (Closed): To take telephonic Interview.)
Taken interview of Vankata. Debashis Bhandari
02:37 PM Redmine Support 1.00 hour (Support #178 (Closed): Miscellaneous Support)
Admin Support Amit Khobragade
10:48 AM Redmine Support 2.00 hours (Support #178 (Closed): Miscellaneous Support)
Followup on author of "Recurring Tasks" plugin. Amit Khobragade

25 Jul 2016

04:33 PM Miscellaneous Activities 1.00 hour (Project: Miscellaneous Activities)
Administration and new tasks discussions with team Rohit Gonsalves
04:30 PM Miscellaneous Activities 1.00 hour (Project: Miscellaneous Activities)
2nd Round Interview of Saddab Gilani. He is selected after the process. Rohit Gonsalves
01:12 PM Redmine Support 3.50 hours (Support #178 (Closed): Miscellaneous Support)
Plugins Research for Redmine. Amit Khobragade

22 Jul 2016

04:47 PM Miscellaneous Activities 1.00 hour (Task #236 (Closed): Conduct 2nd round of interview of Vaibhav Joshi)
2nd Round of Interview is taken by me and Parag. The candidate application is rejected. Rohit Gonsalves
04:35 PM Miscellaneous Activities 1.00 hour (Project: Miscellaneous Activities)
Reviewed the test cases for media looks and discussion on current report. Monday we will receive the report for media... Rohit Gonsalves

21 Jul 2016

04:55 PM Redmine Support 5.00 hours (Support #225 (Closed): New Redmine installation for testing.)
Successfully installed a duplicate copy of existing Redmine. Amit Khobragade
04:48 PM Miscellaneous Activities 0.25 hour (Project: Miscellaneous Activities)
Birthday cake ceremoony - Jignesh Uttam Kamkar
04:45 PM Miscellaneous Activities 1.00 hour (Project: Miscellaneous Activities)
Technical Discussion regarding how to solve this issue; and if there are any workaround with Parag and Debashis. We w... Rohit Gonsalves
04:44 PM Miscellaneous Activities 1.00 hour (Project: Miscellaneous Activities)
Reviewed the LHD4 Bugzilla for Media Sequencer issues and Media looks issues. Rohit Gonsalves
04:43 PM Miscellaneous Activities 2.00 hours (Project: Miscellaneous Activities)
Discussed the problems related to media sequencer with Testers, Parag and Deabshis. Action Item is for Testers to cre... Rohit Gonsalves

19 Jul 2016

05:39 PM Redmine Support 2.00 hours (Support #178 (Closed): Miscellaneous Support)
Amit Khobragade
05:34 PM Redmine Support 4.00 hours (Task #169 (Closed): Implementing "Contents" department in Redmine.)
Amit Khobragade

18 Jul 2016

05:00 PM Redmine Support 3.00 hours (Support #164 (Closed): Discussing "Contents" department workflow.)
Contents department working study/analysis. Amit Khobragade

15 Jul 2016

10:09 AM Redmine Support 1.00 hour (Support #145 (Closed): Meeting with RD.)
checked issues with tracker hider plugin. Amit Khobragade

14 Jul 2016

03:03 PM Redmine Support 3.00 hours (Support #145 (Closed): Meeting with RD.)
Amit Khobragade
 

Also available in: Atom